23.05.2018

Visit of EPoNa site

The participants of the Omusati Investment Conference take the opportunity to visit the EPoNa plant. The different stages of pre-treatment, post-treatment and planned irrigation are explained.

Print Email

17.05.2018

Installation of machinery

All pumps, pips, sensors, etc. are installed by a Namibian company under the supervision of the German manufacturer.

Print Email

23.03.2018

Arrival

Also in Namibia the material is transported with an exceptional convoy and police escort. In Outapi the UASB and micro screen are lifted directly into position.

Print Email

07.02.2018

Shipping

After an intensive preparation the UASB, micro screen and the container with the machinery are transported from Hanau to Hamburg. From there they are shipped directly to Walvis Bay.

Print Email

25.01.2018

Site meetings

Monthly site meetings are held with OTC, consultant, contractor and project partner to document progress and assure the quality of works.

Print Email