20.12.2017

Trailer with skips

Just before Christmas the trailer was delivered with two skips from Windhoek. They will in future assure the transport of the screening material from the micro screen to the fermenter of the ONSRF. There it will be transformed into biogas and subsequently into power.

Print Email

07.11.2017

Dry Beds

The dry beds are constructed to treat the sludge from the UASB. The reinforcement and concrete works of all parts were implemented on site.

Print Email

24.10.2017

Power Line

OTC contracted a local company that extended the power line to the EPoNa site. This will ensure the future operation of all pumps and machinery.

Print Email

18.10.2017

2nd Workshop

The second workshop was held in Outapi and had the following objectives:

·       Common challenges regarding wastewater management

·       Identification of benefits of a wastewater treatment partnership

·       How to address these challenges

Print Email

01.10.2017

Water Supply

 OTC installed the water supply line so that water is available for construction works.